Technical Specs
The Phase 1 development at 2001 Fortune Drive provides 8 MW of critical load; the property has received over $100 million in total investment including seismic, utility, and other capital upgrades. DPR Construction served as the General Contractor. Rosendin Electric and Therma Corporation performed the electrical and mechanical work respectively. EYP Mission Critical Facilities provided commissioning oversight and integrated commissioning testing services.
Data Room Ceiling and Floor
- Floor structural capacity of 2,500 pounds per square foot on slab
- Anti-static VCT throughout Data Room and Corridors
- 100% usable, unencumbered space – no CRAC units on floor
- Air handling systems on segregated equipment mezzanine above Data Room
Electrical/Mechanical Overview
Electrical Feed: PGE Industrial Tariff Primary Service via underground feed. Five substations Primary Service to 480V, 3-Phase. Five substations serve IT Electrical load, one separate substation serve Mechanical load.
Generator Backup: Each of the five substations is backed up by one dedicated generator. A 6th generator will provide N+1 redundancy for the 7 primary generators. Total generation capacity of 15 MW.
Fuel Storage: 24,000 gallons of diesel provide 24-hours of minimum run time at full-load. Additional storage capacity for longer run time available by request.
UPS: High efficiency units deployed modularly with N+1 unit redundancy and alternative delivery path from each of the four substations serving IT electrical load.
Power Distribution Units: Electrical rooms and UPS output sized and circuited for 2N PDU service.
Mechanical and AC Equipment
- Mechanical plant power systems fully segregated from IT power supply (including utility feed and backup).
- 6 Chillers and 6 cooling towers (4,500 ton total capacity) operated at N+1 redundancy.
- 75 Air Handling Units supplied by 6 sets of mechanical switch gear, at N+3 redundancy.
- Four 24,000 gallon tanks provide 96,000 gallons of total make up water capacity.
- Waterside economizer equipment supplements the central plant to further reduce tenant utility costs.
Loading Area
Privately accessed, secured and enclosed with secure storage for on-site receipt.
Fire
- Double interlock pre-action dry pipe fire suppression system for Data Room and Electrical Rooms
- Separate suppression systems on equipment mezzanine
Data Conduit Connectivity
- Committed to carrier neutrality
- Two (2) 4” conduits from tenant space to MMR Standard
- Diverse 4” conduits from the MMR to north and south carrier vaults.
- Multiple carriers in MMR, including AT&T, Level3, AboveNet, Verizon, XO, and other carriers nearby
- Second MMR sited to provide diverse Data Room entrances, loop network architecture
BMS (Building Management System)
24×7 Monitoring of all of the critical equipment, with on-site personnel.
Security
- On site Security Staff and building access 24×7, 365 days per year.
- Recorded, monitored video surveillance of all entrances, building exterior, and interior corridors.
- Multiple layers of authentication access control and surveillance.
- Data rooms may have additional security authentication factors per tenant request


